Marion County I-79 work on schedule, bridge work to continue through winter

FAIRMONT, W.Va. – Construction-induced traffic headaches will continue on I-79 in Marion County between the South Fairmont exit to the Millersville Road exit through October 2024.

DOH Interim District 4 Engineer Mike Daley said work began in July 2021 and the contractor has managed the keep the $72.5 million project on schedule.

Mike Daley

“A lot of the road widening has been completed,” Daley said. “We’re in the process now of building bridges and even through the bad weather, cold weather our contractors are able to work.”

New Kensington, Pennsylvania-based Swank Construction is widening the entire section to six lanes in each direction and rehab work on six bridges. According to Daley, contractors will continue bridge work during the winter months.

“They’re forming, putting rebar in and getting things ready for the concrete,” Daley said. “It doesn’t seem like the weather has effected them that much, they’ve done a great job.”

The section of interstate was first opened in the late 1960s. Use of the corridor connecting Charleston, Morgantown and the Pittsburgh area has skyrocketed as population and commerce have increased.

“It’s needed because of the aging of the bridge structures and the increased capacity in the area we’ve seen,” Daley said.





More News

News
Middle school athletes step out of shot put against transgender girl who just won court case
The situation unfolded at the Harrison County Championships for middle schools, just a couple of days after West Virginia transgender athlete won appeals court ruling.
April 19, 2024 - 2:37 pm
News
West Virginia State University holds a day of community service and giving back
The 11th annual WVSU Cares Day was held Friday at 17 sites throughout Kanawha and Putnam counties.
April 19, 2024 - 2:11 pm
News
Raleigh County judge hears testimony in ongoing Beckley form of government dispute
City's motion to dismiss was considered Friday.
April 19, 2024 - 2:09 pm
News
Union leader refuses to be pessimistic about future of Weirton Cleveland Cliffs plant despite idling of operations
Mark Glyptis believes there will be a mill again as current operation officially idles Saturday.
April 19, 2024 - 12:23 pm