High School Football

Harrison County Commission refuses to issue permit related to dam demolition project

CLARKSBURG, W.Va. — The Harrison County Commission has rejected an application for a permit required as part of a project to demolish three dams along the West Fork River.

The U.S. Fish and Wildlife, along with the Canaan Valley Institute applied for the Location Improvement Permit in October, but the commission held off on making a decision in order to go over the need for one.

According their research, as explained at Thursday’s meeting, the agencies did not need a permit because the federal government can proceed without the county’s permission.

“I don’t think we need to give the permit,” Commission President Ron Watson said. “It would be counter to what we’ve done to save the dams, or save the property owners, whatever number there is out there. Now, if they take the dams out and it destroys and does something with the fence, that’s between the property owner and whoever, Fish and Wildlife.”

In November, the commission passed a resolution designating the river as a lawful fence under state code section 19-17-2 in an effort to save the dams as they have intended to do since the Clarksburg Water Board entered into the agreement with the agencies to tear them down.

However, the statute’s legal authority to block the demolition project is a point of contention.

“It really is about trespass of livestock and liabilities between one land owner and another,” said Todd Miller, Aquatic Restoration Director with the Canaan Valley Institute. “I’m not sure how it pertains to floodplain management or land use.”

The the lone dissent in the 2-1 vote to deny the permit came from Commissioner Bernie Fazzini, who cited the legal retaliation for their actions as cause for hesitation.

However, Watson’s response to that concern was dismissive.

“I’m not surprised,” Miller said. “These projects take a long time and there’s a lot of hurdles to go through. We’ve been through a lot of hurdles already, and I’m sure there’ll be others.”

Despite the setback, the project continues along on through the permitting process as the Location Improvement Permit is not the only one needed to move forward.

Two others remain to be approved, one from the state Department of Environmental Protection and one from the Army Corps of Engineers.

At this point, the plan is to continue to seek the permit from the county, the groups will consult their legal counsel.

“I’m not sure how we’ll address the lack of county permits,” Miller said.

If the permits are secured in the timeline established by the agencies, demolition could happen sometime after the holidays.





More News

News
New intersection makes straight shot onto Buffalo Bridge in Putnam County, eliminates accident-prone intersection
The DOH says there were 37 crashes there in 7 years.
September 19, 2026 - 9:09 am
News
Kanawha County crash claims driver's life
Driver ejected and killed after pickup struck a parked dump truck in work zone.
September 19, 2026 - 9:00 am
News
State lawmaker files formal complaint to PSC against Republic Services
Del. David McCormick says garbage pickup service hasn't improved enough.
September 18, 2026 - 4:10 pm
News
Monongalia County deputy recognized for recent lifesaving efforts
Deputy Steve Pierre jumped into action after EMS cleared the scene.
September 18, 2026 - 1:34 pm