DODDRIDGE COUNTY, W.Va. — A 60,000 barrel per day fracking water treatment plant in Doddridge County is expected to bring hundreds of temporary jobs to the region.
Antero Resources Corporation and Veolia Water Technologies Inc. will construct the facility to take flowback water from drilling and operation sites to be recycled.
“It puts out discharge quality water that would go back into being used in our operations,” explained Antero Resources Corporation Vice President Al Shoop on Thursday’s edition of “Talkline.”
The treatment facility will save Antero an estimated $150,000 per well on future completion costs and generate up to $65 million in earnings.
An estimated 250 workers will be needed to construct the state-of-the art operation. Another 30 to 35 permanent jobs will be created.
“This will be designed specifically for Marcellus and Utica produced and flowback water. So, it is unique in that respect,” Shoop said.
The company reports spending $500 million on buried waterlines that will be ready to redistribute the treated flowback.
Current methods, Shoop predicted, of getting well into well pads and drilling sites will have to be stopped.
“We do believe that injection, which is the predominant method of getting rid of this water is going to be one that’s going to be under challenge here in the next 5-10 years. We believe we found an economical solution. It’s time for somebody in the industry to step up.”
The plant will cut the number of trips truckers make in half.
“Water will be trucked to the plant. All of the water out of the plant will go directly to the pipe, no trucking,” stated Shoop.
While trucks will not be returning for fill ups, Shoop said the number of trucks already hauling wastewater will still be needed.
The $275 million plant could take 2 years to construct.