Harrison County dam demolition project to continue without county permit

CLARKSBURG, W.Va. — A project to demolish three dams along the West Fork River in Harrison County will continue despite the commission’s refusal to issue a permit the agencies applied for.

A letter written to the Harrison County commission was read to them by John Schmidt, Field Supervisor with the U.S. Fish and Wildlife, at their Thursday meeting.

“While we always want to go through the process and make sure we have all of our permits for every project we undertake, they were in fact correct,” he said. “Our lawyers have done the research and it has turned out they are correct. We do not need permits from them.”

This was part of the reason why the commission held off on making a decision regarding the Location Improvement Permit after the agencies involved in the river restoration project applied for it on September 15, 2015.

Because the commission held off past the 90 day limit, a conditional permit was actually issued, but Schmidt told the commissioners they did not need it.

“The federal government is specifically not mentioned as needing permits in both their flood plain ordinance and their Land Improvement Permits.”

As planned, the project would see the demolition of the Highland, Two Lick and West Milford Dams, along with the renovation of the Hartland Dam on behalf of the current owners, the Clarksburg Water Board.

The agreement signed between the two parties would allow the CWB to rid their liability that comes with those three dams and the U.S. Fish and Wildlife would be able to restore to the river for the purpose of protecting the habitat of endangered species.

Some residents along the river, with the support of the county commission, have opposed the project, wanting to see the current water levels in tact for recreational purposes.

Others want the dams for agricultural purposes, such as the natural fence it provides for livestock and the water supply.

Schmidt said while he knows they won’t be able to make everyone happy, they have made an attempt.

“We’ve offered countless times to offer fencing at little or no cost to these landowners. The fact that we’re trying to protect listed species, like the Clubshell and Snuffbox Mussels, would enable to get 100 percent funding from us to get alternative water sources.”

Despite not needing the Harrison County permit, the project is still waiting on a permit from the state DEP –which Schmidt indicated a decision on approval will be made soon– before it can proceed.

The project might also be challenged in court, as the commission as a last-ditch effort to save the dams designated the pools of water behind the dams as lawful fences, based on a section of state code.

There is disagreement over if that designation would actually stop the project.

However, Schmidt remains optimistic that the project will get underway soon.

“I figure we’ll start in March,” he said. “We’ve got to wait until we don’t have freezing temperatures because we anticipate that when we drop the water level, we could strand some mussels in shallow water.”

A significant number of mussels could be lost if the water freezes solid while they remain.

To read a copy of the U.S. Fish and Wildlife’s letter, click here.





More News

News
Hundreds attend Valley Link project meeting in Ranson under shadow of tower-sized banner
Residents and elected leaders express concerns.
November 19, 2026 - 11:32 am
News
Judge rules against Cabell-Huntington again in lawsuit against Big 3 opioid distributors
U.S. District Judge David Faber says AmerisourceBergen, McKesson and Cardinal Health cannot be held responsible for opioid epidemic.
November 19, 2026 - 10:38 am
News
MetroNews This Morning 11-19-26
November 19, 2026 - 6:39 am
News
Mingo County crash claims 2 lives
Wreck happened Wednesday night.
November 18, 2026 - 11:33 pm